Posted on: June 7, 2021

[ARCHIVED] Maryland Avenue Road Project Update

Maryland Ave trails

Maryland Avenue Reconstruction Project

This web page is designed to help provide information on the City of Burlington’s Maryland Ave Reconstruction Project. Information about project tasks and progress shall be shared weekly with the goal of informing property owners and users of public facilities within the project bounds. Should you have any specific questions about your property or construction activities please contact Luke Podella, Staff Engineer with Kapur & Associates, at 262-758-6017 or the City of Burlington Department of Public Works at 262-342-1181.

Maryland Ave trails

Project Description

The City of Burlington began reconstruction of Maryland Avenue on June 1, 2021. This project has substantial completion date of October 15, 2021 and a final completion date of November 15, 2021. This project includes complete reconstruction of Maryland Ave from Congress St to Milwaukee Ave, including new curbs, gutter, and road. Paving of Congress St from Maryland Ave to the dead end cul du sac will also be part of the project. In addition to road improvements, the project will replace the water main, sanitary sewer, and storm sewer infrastructure in Maryland Ave. The project also includes several new pedestrian transportation improvements such as: new sidewalks, on-street painted bike “sharrows”, and a new paved bike trail connection from Maryland Ave to Milwaukee Ave. The gravel semi-truck parking lot will be removed and restored to green space and the corridor will be reforested with several parkway trees.

Traffic and Road Closures

The southern portion of Maryland Ave. near Congress St. is closed to through traffic intermittently while utility work is being performed. Motorists traveling to The Hintz Baseball Complex, Compost Site, or Redmer & Sons Recycling should enter Maryland Ave from the intersection on Milwaukee Ave.

WE Energies Gas and Electric Upgrade Project

WE Energies will be performing gas line and electric line work in Maryland Ave at the same time as the City performs reconstruction. This timing helps minimize the need for WE Energies to disturb the newly constructed roadway. The work performed by WE Energies is separate from the City’s work and is not performed by the City’s contractor, Wanasek, although there will be close coordination between the two projects.

Project Progress (updated 6/21/2021)

As with all construction projects, schedules are subject to change pending weather and other unforeseen impacts. This information is intended to be as accurate as possible but may change from time-to-time. This information will be updated regularly throughout the project and as conditions change. 

  • Planned Work for This Week (6/21/2021) 
    • Complete water service replacements from main to curb stop 
      • Expect water service outages during each service replacement
    • Begin sanitary sewer relay work at Congress St
  • Anticipated Work for Next Week (6/28/2021)      
    • Sanitary sewer relay work entire week
  • Completed Work 
    • Safe sample results obtained for new water main
    • Complete new water main construction
    • Water main connection at Congress
    • Tree and brush removals